Differenze tra le versioni di "Project configuration steps - Estimation"
(→Managed information) (Etichetta: visualeditor) |
(→Managed information) |
||
Riga 36: | Riga 36: | ||
| <u>Item Name</u> || The full textual description of the ''[[glossary|project activity]]''. | | <u>Item Name</u> || The full textual description of the ''[[glossary|project activity]]''. | ||
|| | || | ||
− | |||
− | |||
− | |||
− | |||
− | |||
|- | |- | ||
Riga 53: | Riga 48: | ||
|- | |- | ||
− | | <u> | + | | <u>Duration</u> |
|| The priority of the ''[[glossary|project activity]]''. | || The priority of the ''[[glossary|project activity]]''. | ||
||The list of available priorities can be managed in '''''General/Projects/Activity Priorities'''''. This categorization is useful for scheduling aims. | ||The list of available priorities can be managed in '''''General/Projects/Activity Priorities'''''. This categorization is useful for scheduling aims. | ||
− | |||
− | |||
− | |||
− | |||
|- | |- | ||
Riga 73: | Riga 64: | ||
|- | |- | ||
− | | <u> | + | | <u>Remaining</u> |
+ | || The number of working days (all [[glossary|resources]]) spent. | ||
+ | ||This information is read only and deriving from the ''[[glossary|resources]]''<nowiki/>' ''[[glossary|timesheets]]''. It depends on the date of reference which is set from the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||
+ | |||
+ | |||
+ | |- | ||
+ | | <u>Estimation To complete</u> | ||
|| The number of working days (all [[glossary|resources]]) estimated to complete the ''[[glossary|project]]''. | || The number of working days (all [[glossary|resources]]) estimated to complete the ''[[glossary|project]]''. | ||
||This information is read only. It is actually edited in the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||This information is read only. It is actually edited in the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||
|- | |- | ||
− | | <u> | + | | <u>Estimation At Completion</u> |
|| The number of working days (all[[glossary|resources]]) estimated at the completion of the ''[[glossary|project]]'' (<u>Balance</u> plus <u>ETC</u>). | || The number of working days (all[[glossary|resources]]) estimated at the completion of the ''[[glossary|project]]'' (<u>Balance</u> plus <u>ETC</u>). | ||
||This information is read only. It is actually deriving from the information managed in the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||This information is read only. It is actually deriving from the information managed in the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||
+ | |||
+ | |- | ||
+ | | <u>Delta vs. Budget</u> | ||
+ | || The number of working days (all [[glossary|resources]]) spent. | ||
+ | ||This information is read only and deriving from the ''[[glossary|resources]]''<nowiki/>' ''[[glossary|timesheets]]''. It depends on the date of reference which is set from the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||
+ | |||
+ | |- | ||
+ | | <u>Comment</u> | ||
+ | || The number of working days (all [[glossary|resources]]) spent. | ||
+ | ||This information is read only and deriving from the ''[[glossary|resources]]''<nowiki/>' ''[[glossary|timesheets]]''. It depends on the date of reference which is set from the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||
+ | |||
+ | |- | ||
+ | | <u>Plan to date</u> | ||
+ | || The number of working days (all [[glossary|resources]]) spent. | ||
+ | ||This information is read only and deriving from the ''[[glossary|resources]]''<nowiki/>' ''[[glossary|timesheets]]''. It depends on the date of reference which is set from the ''<u>Estimation</u> ''tab of the ''[[glossary|project]]''. | ||
|- | |- | ||
Riga 103: | Riga 115: | ||
|- | |- | ||
− | | <u> | + | | <u>Confirmed</u> |
|| ''[[glossary|Resources]]'' assigned to the ''[[glossary|project activity]]''. | || ''[[glossary|Resources]]'' assigned to the ''[[glossary|project activity]]''. | ||
|| | || | ||
|- | |- | ||
− | | <u> | + | | <u>Status</u> |
|| ''[[glossary|Project activities]]'' linked as predecessors of the current one. | || ''[[glossary|Project activities]]'' linked as predecessors of the current one. | ||
||In gantt view relationships are shown and managed graphically. | ||In gantt view relationships are shown and managed graphically. | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
|} | |} |
Versione delle 22:19, 29 feb 2016
Estimations are a key tool in order to manage a project. An estimation may contain the figures concerning budget, balance and estimation at completion of working days and financials (to manage financials, the FM - Financial Management module is required).
Estimations can be managed from the Estimation section of the project. Every estimation refers to a spefic Estimation Date which influences the data shown. Actually, data are those calculated at the Estimation Date (e.g. only the timesheets occurring before the date are considered). The key input data managed in an estimation are budget and estimation to complete figures. All other figures are calculated based on them and on balance data which, on turn, derive from timesheets or cost occurrences.
Basic settings
As a first step, it is recommended to check and update the basic settings of the estimations. This can be done with the QUICK ACTIONS command, choosing the Settings selection from the choices available.
Period Estimation Mode
This setting enables the structure of the estimation referring to time. The possible choices are; "Per Project", "Per Year" and "Per Month". "Per Project" means that the estimation data are referring to all the project duration. "Per Year" means that the estimation will be structured in different sections where to plan (e.g. budget) per each year (the numbers of years available will depend on project dates (in particular Internal Operational Start Date and Internal Operational End Date in General section). "Per month means that the estimation will be structured in different sections where to plan for each months. Again, the number of months will depend on project dates.
Detailed Estimation Mode
This setting enable to choose at what level are estimations made. "Per Resource" means that planning data (e.g. budget) are entered with the maximum detail level of the resource. "Per Activity and Resource" means that planning data will be entered at a higher detail level, per activity (according to the work breakdown structure of project activities) and per resource.
Available Sections
This setting allows to define which sections will be present in the estimation. Sections can be included by setting the corresponding checkbox. The available sections are: "Effort", "Expenses" and "Cost Items". "Effort" section allow to manage data concerning working days of resources. "Expenses" sections allow to manage data concerning expenses of resources (e.g. hotel, travel expenses). Finally, "Cost Items" expenses allow to manage specific cost occurrence for the project (e.g. the need to purchase goods or services).
Managed information
The rows of the estimation are automatically built based on data entered in other sections, in particular: Activities for project activities if Detailed Estimation Mode is set to "Per Activity and Resource", Resources for resources added to the project with On Budget property set to "True" and General/Project/Cost Occurrence Categories for cost occurrences.
Columns are predefined but their position can be changed bu drag&drop of their headers. Columns can also be added or hidden by means of the Displays menu to choose visible columns (last right icon of the bottom grid bar).
Available columns are described below.
Field | Description | Comment
|
---|---|---|
Task Name | This is the name. | Mandatory. |
Item Name | The full textual description of the project activity. | |
Start Date | The start date of the project activity. | Mandatory. |
End Date | The end date of the project activity. | |
Duration | The priority of the project activity. | The list of available priorities can be managed in General/Projects/Activity Priorities. This categorization is useful for scheduling aims.
|
Budget | The number of working days (all resources) budgeted. | This information is read only. It is actually edited in the Estimation tab of the project. |
Balance | The number of working days (all resources) spent. | This information is read only and deriving from the resources' timesheets. It depends on the date of reference which is set from the Estimation tab of the project. |
Remaining | The number of working days (all resources) spent. | This information is read only and deriving from the resources' timesheets. It depends on the date of reference which is set from the Estimation tab of the project.
|
Estimation To complete | The number of working days (all resources) estimated to complete the project. | This information is read only. It is actually edited in the Estimation tab of the project. |
Estimation At Completion | The number of working days (allresources) estimated at the completion of the project (Balance plus ETC). | This information is read only. It is actually deriving from the information managed in the Estimation tab of the project. |
Delta vs. Budget | The number of working days (all resources) spent. | This information is read only and deriving from the resources' timesheets. It depends on the date of reference which is set from the Estimation tab of the project. |
Comment | The number of working days (all resources) spent. | This information is read only and deriving from the resources' timesheets. It depends on the date of reference which is set from the Estimation tab of the project. |
Plan to date | The number of working days (all resources) spent. | This information is read only and deriving from the resources' timesheets. It depends on the date of reference which is set from the Estimation tab of the project. |
% Complete | The percentage (Balance / EAC) of work completed of the project. | This information is read only. It is actually deriving from the information managed in the Estimation tab of the project. |
Planned % Complete | The percentage of work theoretically planned to be completed of the project. This is the Plan to date work divided the Budget work multiplied 100. | This information is read only. It is actually deriving from the information managed in the Estimation tab of the project. |
Earn | This is a key performance indicator representing the efficiency of the work. It is calculated as Budget work divided Estimation at Completion work. If minor than one the efficiency (work spent) is lower than expected. Higher on the contrary. | This information is read only. It is actually deriving from the information managed in the Estimation tab of the project. |
Earned Value | The value, in working days, of the work done. It is calculated as Budget divided Estimation at Completion multiplied Balance. | This information is read only. It is actually deriving from the information managed in the Estimation tab of the project. |
Confirmed | Resources assigned to the project activity. | |
Status | Project activities linked as predecessors of the current one. | In gantt view relationships are shown and managed graphically. |